Mumbai Infra Update: Mahalaxmi Cable-Stayed Flyover Opening Delayed To December 2026 Due To Utility-Shifting Work
BMC has revised the opening of Mumbai’s first cable-stayed flyover near Mahalaxmi Railway Station from October 31 to December 31, 2026, after utility-shifting work caused a two-month delay. Construction of the 78.5-metre pylon and western span is progressing, while work on the eastern span awaits Railway clearance.