Mumbai Infra Update: Sion Railway Over Bridge Second Girder Set For August 8-9 Midnight Launch, Opening Delayed Until End-September
The second steel girder of Mumbai’s delayed Sion Railway Over Bridge is scheduled to be launched during the August 8-9 midnight rail block. However, the BMC needs another 45 days to complete approach roads and related works, pushing the bridge’s reopening from the earlier August 15 target to the end of September. The project cost has risen from Rs 42.8 crore to nearly Rs 50 crore.