Mumbai BMC Projects See Nearly ₹148 Crore Cost Escalation, Opposition Questions Flyover Expenses & Financial Accountability

Mumbai BMC projects have recorded cost escalations totalling ₹148.18 crore, largely involving flyovers. The biggest increases include ₹53 crore for Ashray Yojana and ₹38 crore for Mrinaltai Gore flyover. Opposition parties have demanded scrutiny of delays and contractor practices, while civic officials say some additional costs arose from encroachments and other project hurdles.

Videos

Mumbai BMC Projects See Nearly ₹148 Crore Cost Escalation, Opposition Questions Flyover Expenses & Financial Accountability
5 Minuten 2 Sekunden

Mumbai BMC Projects See Nearly ₹148 Crore Cost Escalation, Opposition Questions Flyover Expenses & Financial Accountability

Weekly Legal Round-Up: Cream Centre Case, ₹1.79 Cr MACT Award & Major Mumbai Court Rulings
9 Minuten 18 Sekunden

Weekly Legal Round-Up: Cream Centre Case, ₹1.79 Cr MACT Award & Major Mumbai Court Rulings

Ähnliche Seiten

https://www.freepressjournal.in/mumbai/mumbai-infra-update-bmc-standing-committee-approves-second-cost-hike-for-andheri-flyover-repairs-project-cost-rises-to-13036-crore

Mumbai Infra Update: BMC Standing Committee Approves Second Cost Hike For Andheri Flyover Repairs; Project Cost Rises To ₹130.36 Crore

https://www.freepressjournal.in/mumbai/mumbai-infra-update-bmc-standing-committee-approves-second-cost-hike-for-andheri-flyover-repairs-project-cost-rises-to-13036-crore
https://www.freepressjournal.in/mumbai/mumbai-flyover-repairs-bmc-hikes-project-cost-by-52-per-cent-to-4803-crore-extends-deadline-to-march-2027

Mumbai Flyover Repairs: BMC Hikes Project Cost By 52 Per Cent To ₹48.03 Crore, Extends Deadline To March 2027

https://www.freepressjournal.in/mumbai/mumbai-flyover-repairs-bmc-hikes-project-cost-by-52-per-cent-to-4803-crore-extends-deadline-to-march-2027
https://www.freepressjournal.in/mumbai/mumbai-infra-update-bmc-approves-flyover-repairs-despite-52-per-cent-cost-hike-in-sclr-estimate-to-4803-crore

Mumbai Infra Update: BMC Approves Flyover Repairs Despite 52 Per Cent Cost Hike In SCLR Estimate To ₹48.03 Crore

https://www.freepressjournal.in/mumbai/mumbai-infra-update-bmc-approves-flyover-repairs-despite-52-per-cent-cost-hike-in-sclr-estimate-to-4803-crore